CoreSynaptics Coresynaptics
DEMO ORG
L1RED TAG
FAT
L1
L2YELLOW TAG
Receipt Inspection / SIP
L2AL2BL2CL2D
L3GREEN TAG
Energization and Startup
L3
L4BLUE TAG
Functional Testing
L4
L5WHITE TAG
IST & Acceptance
L5
L6SLATE TAG
Clean walk + handover
L6

HOW THIS WORKS

The whole spine, top to bottom, with your seat marked on it.

THE ONE SENTENCE · IF YOU REMEMBER NOTHING ELSE

Readiness opens the gate, not the schedule. Everything below is that sentence made mechanical: evidence is captured first, the checkmark is created last, and a gate opens when the system is ready rather than when the date arrives.

PROCESS HIERARCHY · LOADING

Loading the spine…

WHERE YOUR GATES SIT · NO CX GATES — CONSTRUCTION LANE

Your company owns no commissioning gates. That is correct and normal — earthwork, concrete, steel, envelope and design all work on this project without ever signing a Cx gate. You still file submittals, pull permits, log daily reports and receive findings.